— 25 —

Rayak—Homs—Hama Line.

In the autumn of 1902 the station Rayak of the Beirut—Damascus railway was connected with the towns of Homs and Hama — the centres of the grain-rich Orontes plain — by a railway 188 km long. It is later to be extended northward as far as Aleppo, and southward, by way of Rascheja, Hasbeja, Nazareth and Nabulus, as far as Jerusalem. The construction of this railway was taken in hand in 1901 and carried out so quickly that the whole stretch Rayak—Hama could be given over to traffic in October 1902. It is later to be joined to the Konia—Baghdad line and is for that reason of standard gauge. By means of the new line, considerable quantities of grain from the region of Homs and Hama — which were formerly transported by camel to Tripolis — have already been conveyed to Beirut and, after storage, shipped thence as required.

The Baghdad Railway.

On the 14th of December 1903 the constituent assembly of the Baghdad Railway Company took place in Constantinople. The Turkish government furnished sufficient pledges for the kilometre-guarantee, and the project — long since followed in wide circles with great interest — was brought forward a considerable stretch. The concession has now been transferred from the Anatolian Railway Company, which had already begun the construction of the section Konia—Eregli before the constitution of the new company, to the Société of the Baghdad Railway.

As is known, the negotiations between the German and French financial groups could for a long time come to no conclusion. It was a question of the amount of the capital participation on either side. Originally the German group was concerned in the business with 60%, the French group with 40%, of the investment capital. The German group commanded not only the majority but also had the direction of the undertaking in its hands. Now a change has entered into this relation. Each of the two groups has ceded a 10% participation to Austrian, Swiss, Italian and Turkish capital circles, so that in future — including the share of the Anatolian railway company — only 50% of the business falls to the German group, 30% to the French, and 20% to the financial groups of other countries. The German group will accordingly no longer command the majority of the share capital, but neither can it be outvoted by the other side.

The construction of the first section of the Baghdad railway is made possible on the part of the Porte by a Turkish loan of 50 million francs, which a syndicate — under the leadership of the Deutsche Bank, the Ottoman Bank, the Wiener Bankverein and the Swiss Kreditanstalt — had taken over.

In Frankfurt a. M. a construction company constituted itself, as a company with limited liability with a capital of 3 million marks, to which the great consortium that has set itself the realization of the Baghdad railway from Konia to the Persian Gulf has entrusted the construction of the first 200-km-long section of the Baghdad railway, Konia—Eregli. As already mentioned above, the construction of this section — which requires an outlay of about 43 million marks — was begun some time ago, and the financing of the building-costs will take place on the basis of the above-mentioned loan.